July 2018 News

29 July 18 Print

July 2018 News

July 2018 News

Organizing weekly engineering sessions with the presence of project partners and reviewing project implementation issues
Morning meeting in the presence of the CEO to present the weekly work program of the project
Establishing regular HSE weekly meetings to protect the safety of workers and workshop personnel
Follow up on the facade commission from the municipality and obtaining a confirmation from the Municipal Commission
Personnel, Employer, Consultant Preliminary Training on Wednesdays
Establishment of engineering sessions with the presence of the CEO and the consultant in order to stabilize the future of the project
Continued execution of the installation of metal skeleton, concrete laying in ceilings and walls
Implementation of the wall posts and block wall and installing support for piping underground floors and pinch cable for the floors of the negative floors
Doing grubbing in the -9 floor
Examining the work table for the negative classes
Track purchasing workshop lift
Height towers 16 tons and 12 tons for more efficiency
Preparation of concreting concretes for the final floor of the negative floors, including installing the concrete pump, mounting the mesh, and formatting and corresponding zoning.
Visiting and controlling the quality of fireproof materials from Shahid Rajaee port and carrying it to the workshop
Run fire coatingon the floors -3 to -8
Checking for a contract for a sewage pre-treatment system