Conduct a concurrency co-ordination meeting between contractors and employer on Tuesday
HSE co-ordination meetings with contractor on Mondays
Follow up of planning coordination and project control meetings
Weekly engineering sessions with the presence of CEO and Consulting Engineers Group 4

Establishing project scheduling sessions with the presence of the plan and contractor office and reviewing the performance of the contractors
Study of the maps and sessions of the working group with the internal units of the hospital to perform the hospital's work and set up the minimum requirements
Visiting Aran Sajz Factory, metal construction contractor
Visit factories to build electricity boards to buy electricity boards needed for the project before bidding
Formation of commission for purchases required for the project
Meeting with the Municipality Partnership on Tables of Levels and Levels of the Project
Follow up and eliminate the new lawsuit from the municipality and the public participation organization
Tracking the required power for the project at 2.6 MW
Follow the sewage project splits
Implementation of electrical and mechanical systems in negative classes
Implementation of fireproofing in the negative classes
Implementation of wall-mounting and installation of wall posts in negative classes
The execution of the metal structure and the ceilings of the twelfth stage(floors 17 and 18)