February 2019 News

February 2019 News
Organizing weekly engineering sessions on executive issues and project technical drawings
Follow up of the municipality for a license to increase the density and non-compliance
Assessment of the most desirable option to power up the project by Niroo Consulting Engineers
Visit glass companies to buy glass for the building facade
Conducting expert meetings on materials and facade engineering
Holding several meetings with qualified consultants for the implementation and obtaining of a license for project helipad
Concrete project roofs with the highest record and efficiency in the past months
Holding safety briefings with project partners
Tracking of sewage branching and obtaining drilling license from the municipality of the region
Check the maps by firefighters and review the approved project plans
Assessment of the future tender documents including fireproofing and the implementation of electrical and mechanical equipment and joinery
Obtaining a permit from the traffic police to conduct operations during day and night