2 December 20 Print

October 2020 News

October 2020 News

- Operations related to buildings and facilities in the +1 to +5 floors are underway.
- The total progress in the +1 and +2 classes is about 77%.
- The total progress in the +3 to +5 classes is about 53%.
- Facade installation operations are underway and have been carried out up to the 16th floor.
- The overall progress of the project is about 58%.
- The total progress of Unite facade installation is about 53%.
- The total progress of the installation of the stick facade is about 54%.
- Operations related to firecrackers in classes -1 and -2 are underway and the overall progress is 90%.
- Notification of the contract related to the implementation of the elevator, placement in the workshop and purchase of hardware needed for the implementation
- Notification of the contract related to the implementation of Valkrit, classes +16, +17, +18, establishment in the workshop for implementation