June 2021 News

June 2021 News

- Floor +2
Installation of support and implementation of fresh air ducts, elastomeric insulation of fresh air ducts, implementation of support and plumbing of 5-layer pipe system, implementation of elastomeric insulation of 5-layer pipe system, implementation of elastometric insulation of steel pipes, installation of manual dampers And duct fire went, installation of manual dampers and return duct fire, implementation of elastomeric insulation of return air duct and evacuation
- Floor +5:
Execution of cabling (power supply of electrical panels from the floor), implementation of support and piping of water supply system (galvanized pipe), implementation of elastomeric insulation of water supply system (galvanized pipe), implementation of support and plumbing of 5-layer pipe system, implementation of elastomeric insulation of pipe system Of 5 layers, implementation of steel plumbing, implementation of medical gas system control box, installation of manual dampers and fire channel, installation of manual dampers and return channel fire
- Floor +6:
Water supply system piping (galvanized pipe), fire system piping (firebox piping), sprinkler system piping, medical gas system piping
Execution of elastomeric insulation of fresh air ducts, installation of pipes and cans of switches and sockets, implementation of cable trays, implementation of steel piping, installation of manual dampers and fire ducts, installation of manual dampers and return ducts
- Floor +8:
Execution of cabling (network system), execution of pipes and cans of switches and sockets, execution of floor cabling, execution of cabling (telephone system), execution of wiring, execution of electrical installations
- The facade installation operation is underway and has been completed up to the 26th floor, and the overall progress of the project facade has reached about 85%.
- Hardening operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 24%.
- Joinery operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 14%.