December 2021 News

December 2021 News

- Floor +2:
- Implementation of waterproofing
- Apply floor protective mortar
- Ceramic execution
- Execution of cabling (power supply of electrical panels from the floor)
- Wiring implementation (lighting system)
- Execution of wiring (electrical system)

- Floor +3:
- Execution of cabling (power supply of electrical panels)
- Wiring implementation (lighting system)
- Execution of wiring (electrical system)
- Execution of support and plumbing of 5-layer pipe system
- Execution of elastomeric insulation of 5-layer pipe system
- Execution of elastometric insulation of steel pipe
- Execution of medical gas system pipe
- Execution of wiring (audio system)
- Execution of fan coil

Floor +5:
- Execution of support, pipes and cans of switches and sockets
- Execution of supports and cable trays
- Execution of cabling (power supply of electrical panels from the floor)
- Wiring implementation (lighting system)
- Execution of wiring (electrical system)
- Execution of elastometric insulation of steel pipe
- Execution of medical gas system pipe

- Floor +6:
- Wiring implementation (lighting system)
- Execution of wiring (electrical system)
- Wiring (UPS system)
- Execution of elastomeric insulation of water supply system (galvanized pipe)
- Execution of medical gas system pipe
- Execution of cabling (fire alarm system)

- Floor +7:
- Execution of corrugation to execute sewer pipes
- Execution of Knauf wall substructure
- Install subframe

- Floor +18
- Execution of interior wall foundation wall
- Execute the color of the mosaic flooring wall of the western electrical room
- Installation of support and execution of eastern zone sprinkler piping
- Execution of electricity pipes in the western zone corridor
- Execution of hot and cold water piping for eastern zone corridor services
- Execution of sewage piping of corridor services in the western zone
- Installation of joint support in the eastern zone corridor

- Class +19:
- Execution of wall paint, flooring, oriental electrical room mosaic
- Execution of wall paint, flooring, mosaic of western electrical room
- Execution of electricity pipes in the western and southern corridors

- Implementation of facilities related to parking lots, clinics and hospitals is underway and the overall progress has reached about 29%.
- The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached an overall progress of 33%.
- The implementation of electrical installations related to parking lots, clinics and hospitals has reached an overall progress of 25%.