May 2022 News

5 July 22 Print

May 2022 News

May 2022 News

Negative floors and ground floor:
- Implementation of the masonry wall of the 4th floor-
- Implementation of EN7 and EN13 elevator wall paint on the ground floor
- Implementation of Kenaf EN7 wall color on the ground floor

Floor +1:
- Implementation of wiring (lighting system)
- Implementation of UPS system wiring
- Implementation of elevator wall color EN13 and EN7
- Implementation of Kenaf wall color EN7

2nd floor:
- Implementation of elevator wall color EN13 and EN7
- Installation of Kenaf wall infrastructure EN5
- Execution of installation of Kenaf wall infrastructure EN6
- Implementation of Kenaf wall color EN7

3rd floor:
- Implementation of elevator wall color EN13 and EN7
- Implementation of EN6 Kenaf wall installation
- Implementation of Kenaf wall color EN7

4th floor:
- Implementation of wiring (electrical system)
- Implementation of wiring (lighting system)
- Implementation of elevator wall color EN13 and EN7
- Implementation of EN6 Kenaf wall installation
- Implementation of Kenaf wall color EN7

5th floor:
- Implementation of elevator wall color EN13 and EN7
- Implementation of EN6 Kenaf wall installation
- Implementation of Kenaf wall color EN7

6th floor:
- Implementation of elastometric insulation of steel pipe
- Construction and installation of channel risers and positive pressure of the staircase
- Implementation of EN3 and EN7 elevator wall color
- Implementation of EN6 Kenaf wall installation
- Implementation of Kenaf wall color EN7

7th floor:
- Implementation of elastomeric insulation of fresh and outgoing air channels
- Implementation of fire system piping (firebox piping)
- Implementation of elastomeric insulation of the 5-layer pipe system
- Implementation of piping system of 5-layer pipes
- Installation of fresh and exhaust air channels
- Implementation of the Kenaf wall
- Performance of stone wool
- Implementation of piping system of 5-layer pipes
- The physical progress of the whole project is 67%.
- The hardening operation related to the parking lots, clinic and hospital is being implemented and the overall progress has reached about 43%.
- Fine work operations related to parking lots, clinic and hospital are being implemented and the overall progress has reached about 28 percent.