August 2022 News

August 2022 News

2nd Floor :
- Implementation of the motor house loop structure
- Construction of condensate source water supply collector
- Construction of air separator chassis (AIR SEPARATOR)
- Installation of cooling system flange and gasket
- Installation of strainer and shock absorber of the cooling system
- Installation of cooling system valves
- Installation of saddles under the cooling system piping
- Construction of cooling system collector
- Implementation of cooling system pipelines on supports
- Installation of strainer and vibration absorber of the heating system
- Installation of heating system valves
- Initial installation of piping supports for the heating system
- Making saddles for heating system piping
- Installation of saddles under the heating system piping
- Construction of heating system collector
- Implementation of heating system pipelines on supports
- Construction of the chassis of the boiler water discharge tank (BLOWDOWN)
- Installing the boiler water drain tank on the chassis (BLOWDOWN)
- Installation of steam system valves
- Initial installation of piping supports for the steam system
- Making saddles for steam system piping
- Installation of saddles for steam system piping
- Implementation of steam system pipelines on supports
- Initial installation of piping supports for the soft water system
- Making saddles for soft water system piping
- Installation of soft water system piping saddles
- Implementation of soft water system pipelines on supports
- Installation of soft water system flange and gasket
- Installing the flange and gasket of the water supply system
- Initial installation of piping supports for the water supply system
- Construction of saddles for water supply system piping
- Installation of saddles under the water supply system piping
- Construction of water supply system collector
- Implementation of water supply system pipelines on supports
- Initial installation of piping supports for the sprinkler system
- Construction of sprinkler system piping saddles
- Implementation of sprinkler system pipelines on supports
- Initial installation of piping supports for the fire fighting system
- Construction of saddles under the fire system piping
- Implementation of fire system pipelines on supports
- Initial installation of fuel system piping supports
- Implementation of fuel system pipelines on fuel
- Construction of elbow of condensate source pipeline
- Installing the knee of the cooling system
- Construction of heating system, steam, soft water, water supply, sprinkler and fuel system

Floor +3 to +6:
- Implementation of zone D waterproofing
- Implementation of floor protective mortar in zones B and D


7th floor:
- Implementation of B C D mosaic zones
- Flooring of the dry space of B D zones
- Flooring of the wet area of B C D zones
- Implementation of plaster of Kenaf wall of the second layer of the first face MR-RG-FR-FM of the interior space
- Implementation of leaf plaster of the Kenaf wall of the first layer of the second face MR-RG-FR-FM of the interior space
- Implementation of wiring (lighting system)
- Implementation of wiring (Prisbarg system)
- Carrying out cabling (supplying electrical panels)
- Implementation of fire system piping (firebox piping)
- Implementation of the sprinkler system pipe

Floor +18 and +19:
- Implementation of dry space false ceiling panel in offices B2-B4-B5-B6-B8-B10-C4-C5-C7
- Implementation of false ceiling panels in the wet space of the office C4-C9-A1-A2-A3-A10-A6-A7-A8-C1-C2-C3
- Implementation of ceramics for the body of the corridor in the south zone (on the side of ducts, offices)
- Implementation of ceramic body of the wet spaces of offices C1, C2, C3
- Implementation of ceramic office body B4-B5-B6-C4-C5-C6-C7-C9-A7-A8
- Implementation of ceramic floor of the office dry space B10-B5-B6-B7-B9-C10-C4-C5-C6-C9
- Implementation of office floor ceramics B8-C10-C4-C5-C7-C9-A8
- Implementation of the false ceiling chassis of the dry space of the office B1-B10-B2-B3-B4-B5-B6-B8-C5
- Implementation of false ceiling chassis wet space office B9-C9-A1-A2-A3-A7-A8-C1-C2-C3
- Implementation of moisture insulation of the wet space of the office B1-B10-B2-B4-B6-B7-B9
- Implementation of the moisture insulation protective layer of the wet space of the office B10-B4-B5-B6-B7-B9-C7-C9


Phase one operation:
- Implementation of the false ceiling chassis of the 4th floor-
- Implementation of the false ceiling panel on the 4th floor-
- Painting the false ceiling on the 4th floor-
- 4th floor fire alarm cabling
- Installing lights on the 4th floor-
- Installing the fire box on the 4th floor-
- Painting the wall of the central zone
- Painting the roof of the northern ramp
- Installation of northern ramp lights
- Implementation of the mineral infrastructure of the wall of the northern staircase No. 1
- Implementation of the wiring of the lighting system of the northern staircase of the central zone No. 1
- Installation of positive pressure air channel in the northern staircase of central zone No. 1
- Implementation of the infrastructure of the wall of the elevator door EN1
- Execution of the wall panel of the elevator door EN1
- The physical progress of the whole project is 69.51%.
- The implementation of facilities related to parking lots, clinic and hospital is being implemented and the overall progress has reached about 41%.
- The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached a total progress of 46%.
- The implementation of electrical facilities related to parking lots, clinics and hospitals has reached a total progress of 37%.