28 June 25 Print

April 2025 News

April 2025 News

• Continuing internal gas piping operations and conducting pipe welding tests under the supervision of the engineering system supervisor
• Installing low-pressure electrical panels in the engine room
• Planning to start the second compression chiller on the roof
• Continuing execution operations on the hospital floors (including floors 10-11 and 13)
• Continuing construction of the project's air conditioners and reaching a progress rate of 55%
• Planning for temporary delivery of floor 22+
• Continuing installation of project elevators
• Continuing execution operations on floor 9+ (air conditioner rooms)
• Planning to install two diesel generators on floor -2
• Continuing execution operations on the west and east sides of floor 17+
• Continuing execution operations on the central zones of floors 18+ to 20+
• Continuing execution operations on the engine room
• Planning to test 1 absorption chiller in the engine room and completing the reinforcement of the second chiller cover
• Complete assembly of water tanks on floor 16+ and planning for installation Inputs and outputs
• Continue construction of electrical panels for the first phase of operation and delivery of 11 electrical panels
• 50% of steam valves for the engine room
• Signing and notifying contracts for floors 1+ to 3+
• Coordination for the assembly of air handling units with Rifle Company and dispatching relevant experts
• Notifying the implementation of weak current to Payasazeh Company to start and continue GPON infrastructure operations
• Signing a contract to purchase the remaining ducts with Lenazd Company
• Arranging an addendum to the helipad lighting contract

 Floor -6:
Executing primer under the work
Executing earth bonding

 Floor -2:
Full welding of engine room pipelines
Installing valves, strainers, flanges, etc.
Executing saddles for engine room pipes
Executing pipe rack piping
Electricity and installation of support and engine room tray

Floor -1:
Executing steel pipelines
Executing floor screed
Repairing the sleeping floors
Concrete pouring for the wet area
Knauf wall panel installation
Cementing the walls
Electrical plumbing for the holding areas

 Floor +11:
Galvanized pipeline and 5-layer pipe and natural gas
Knauf wall panel installation
Water supply pipe insulation
False ceiling structure installation
Console installation
Common support installation
Electrical plumbing and wall support installation
Central side falsework installation

 Floor +13:
Floor runner installation
Knauf wall foundation installation
Sewerage pipeline installation

 Floor +16:
Fire cistern construction

 Floor +18:
Support, tray and electrical pipe installation for the central zone
Ceramic installation for the central side garbage room wall
Electrical tray and electrical pipe installation for the central zone

 Floor +21:
Final wall painting installation
Cementing Central side garbage room

 Floor +23:
Installation of mosaic floor in electrical room
Installation of ceramic floor and body
Installation of corridor panel
Installation of wiring and fixing defects
Installation of plaster surface

 Floor +24:
Installation of ceramic body and wall in central side
Installation of false ceiling panel in corridor
Installation of wiring and fixing defects
Installation of false ceiling chassis

The physical progress of the entire project is 82.47%.
The overall progress of the solidification and thinning operations has reached 80 and 62 percent, respectively.