• Continue construction of the project's air conditioners and reach a progress rate of about 70%
• Continue to fix the 22nd floor's defects
• Continue to install the project's elevators
• Continue to execute the 9+ floor's (air conditioner rooms) and bring galvanized pipes to the workshop
• Plan to install two diesel generators on the 2nd floor and hold meetings with the supplier for ventilation and exhaust paths for the generators
• Continue to execute the west and east sides of the 17+ floor
• Continue to execute the central zones of the 18+ to 25+ floors
• Continue to execute the 6- floor's (parking lot)
• Lighten the cylindrical facade of the tower and the stick facade and plan to fix minor defects
• Continue to construct the electrical panels of the first phase of operation floors and deliver 80 electrical panels
• Hold multiple meetings with the project's BMS consultant regarding water vapor control valves
• Continue to install the air conditioner in the air conditioner room on the 1+ floor and the 1- and 3+ floors
• Continue GPON infrastructure operations on floors 11-10-7 and -1 and ground floor
• Start of helipad lighting operations
• Continue VRF installation operations on the eastern slope of 17+
• Continue construction of roof condensing boilers by Pakman Company and meeting with the company's management to expedite the delivery of boilers
• Delivery of all monorail climber baskets
• Preparation for installation of 2 plate exchangers on floor 9+
• Negotiation with Payasazeh Company regarding the prices and contract amounts for floors 8+, 16 and the roof
• Continue service and maintenance operations for equipment installed in the workshop with Payasazeh Company
• Preparations for installation of waste disposal devices on floor 2-
• Notification of the addition of Rifle Company to expedite the construction of the remaining 33 air conditioners
• Preparation of a purchase contract for 80 automatic doors in the first phase
• Negotiation with cdoor Company to purchase plywood doors for inpatient rooms
• Visit to projects of 3 leading companies supplying fresh air to parking lots
• Opening of tender envelopes for the purchase of the remaining panels of the second phase of the project
• Planning for the purchase of all control valves of the project
• Continuing the construction of electrical panels for the hospital floors
• Continuing the implementation of antenna reinforcement for the floors of the doctors' building
Floor 2-:
Implementation of the drainage and ventilation piping of the air conditioner and fan coil and its testing
Implementation of wallpapering
Implementation of the porcelain wall of the incinerator room
Floor 1-:
Implementation of sewage
Implementation of insulation of the laundry and sanitary floors
Implementation of sound insulation
Installation of supports and trays
Installation of the air conditioner room panel
Floor 1+:
Implementation of the substructure of the Knauf ceiling
Implementation of porcelain wall
Installation of supports and pipes
Floor 7+:
Implementation of insulation of channels and pipes
Implementation of the sewage pipeline
Implementation of the false ceiling panel
Implementation of cementing
Floor 13+:
Implementation of insulation of channels
Implementation of trays, supports and Pipe
Mosaic installation
Installation of medical, galvanized and 5-layer gas lines and firebox
Floor 17+:
Installation of medical gas
Installation of ceiling and wall pipes and supports
Installation of plastering and falsework
Floor 22+:
Installation of bathroom doors
Floor 23+:
Installation of ceiling putty and putty
Installation of ceiling inspection hatches
Plastering
Installation of ceramic floor
Installation of bathroom doors
Installation of window flashing
Floor 25+:
Installation of ceramic floor in wet areas
Installation of supports and pipes
Floor 26+:
Installation of supports and saddles for cooling tower pipes
The physical progress of the entire project is 83.78 percent.
The overall progress of the facility has reached about 75 percent.
The implementation of mechanical and electrical installations has reached an overall progress of 77 and 72 percent, respectively.