• Completing the internal gas piping operations and submitting the documentation to the engineering system for route approval
• Continuing the construction of electrical panels for the first phase of operation and delivery of all electrical panels
• Continuing the assembly operations of the project's air conditioners in the workshop
• Installing and positioning roof condensing boilers
• Manufacturing insulated panels by TTM Company, delivering them to the workshop and installing 60 pieces
• Planning to purchase all project control valves
• Completing the main electrical connection of the project in the entire building circuit
• Planning to purchase fireproof doors for the first phase of the project
• Starting the assembly of the labor camp on the ground floor
Floor 1-:
Implementing the foundation and installing the Knauf ceiling panel
Completing the floor ceramic
Implementing the type and putty and painting
Installing and capping the electrical panels
Installing the vents
Installing the lights
Floor 1+:
Implementing the foundation and installing the false ceiling panel in the southern zone
Implementing the foundation of the false ceiling in the central zone
Implementing the floor ceramic
Implementing the type and putty and painting of the southern zone
Implementation of fireproofing and smokeproofing of the ceiling seams and electrical and mechanical elements
Installation of dry ceramic on the southeast side of the ramp
Installation of the southeast ramp louver
Construction and installation of the operating room channel in the southern zone
Construction and installation of the square valve box and installation of the central zone flexi
Implementation of network cabling
Floor 3+:
Implementation of cementing and ceramic on the central zone wall
Implementation of ceramic on the communication corridor wall and the elevator lobby corridor on the northern side
Implementation of smokeproofing of the risers
Floor 8+:
Implementation of reinforcement, formwork and concreting of the floor of the air conditioning room in the eastern zone
Installation of supports, trays and elevator panels
Implementation of the earthing cable
Floor 9+:
Implementation of the installation of the air ducts in the eastern zone
Implementation of the insulation of the air ducts in the eastern zone
Implementation of water supply lines, sprinklers and H&K lines
Implementation of plate exchanger lines
Implementation of full welding of the lines implemented
Construction and installation Air conditioner chassis and installation of air conditioner in the western zone
Floor 10+:
Installation of ceiling panels in the central zone
Application of mastic and sealant on the central zone ceiling
Application of ceramic tiles on the central zone floor
Installation of interior panels around electric doors
Installation of rounding and installation of vents
Installation of lights
Installation of medical gas in the eastern zone
Installation and capping of electrical panels
Floor 16+:
Installation of support for pump house installations
Installation of sliders for pump house pipes
Floor 17+:
Installation of ceiling panels in the central zone
Painting of the ceiling in the central zone
Plumbing of the radiology room and CT-scan in the eastern zone
Underpinning of the ceiling and wall in the eastern zone
Application of mastic and putty on the ceiling and wall in the eastern zone
Plastering of the imaging section in the eastern zone and plastering in the western zone
Construction and installation of square vent boxes and installation of flexi pipes in the eastern zone
Implementation of defect removal and completion of the electrical infrastructure in the zone West
Implementation of the substructure of the elevator lobby ceiling in the West Zone
Implementation of fusion and installation of the modem in the East Zone
Testing of fiber optic cables
Installation and termination of the electrical panels in the East and West Zones
Floor 23+:
Installation of the office skirting boards
Implementation of fixing painting defects
Implementation of fixing electrical installations
Floor 26+:
Implementation of the roof engine room wall
Implementation of epoxy coating on the roof engine room floor
Transferring and moving air conditioners, coil sources and boilers from the ground level to the location on the 26+ floor
Moving and positioning coil sources and boilers in the roof engine room
Performing full welding of the roof chiller lines