June 2026 News

June 2026 News

• Installation and placement of roof engine room equipment
• Continuation of executive operations on the hospital floors (including floors 10-11 and 13)
• Continuation of executive operations on the central zones of the floors, engine room, floors 1+ to 3+, facilities on floors 16+ and the roof
• Operation of the new labor camp and deployment of forces
• Continuation of installation of project elevators and reopening of passenger elevators
• Implementation of Knauf and ceramic walls, gas riser walls on the floors
• Continuation of construction of project air conditioners and delivery of 51 units from Rifle Company
• Continuation of installation of air conditioners in the air conditioner room on the 9+ floor
• Continuation of construction, installation and termination of electrical panels on the hospital floors
• Construction of isolated panels by TTM Company, delivery to the workshop and installation of 132 pieces
• Continuation of GPON infrastructure operations on floors 11-10-7 and -1
• Purchase of doors on floors 7+, 1+ and -1
• Delivery process of the 24th floor

Floor 2-:
Implementation of diesel fuel filler piping connected to the riser
Implementation of supporting pipes and installations of the engine room
Implementation of ironwork, installation of sheet metal and tarpaulin around the radiator of diesel generators
Implementation of doors and painting of diesel generator rooms
Implementation of the Siamese fire line piping
Installation of steam traps for air conditioner lines
Implementation of 5-inch galvanized sewage piping
Utilization of the new labor camp and deployment of forces

Ground floor:
Dismantling of the equipment of the former workshop
Implementation of the cooling of the service area of the former labor camp
Implementation of the eastern side wall post

Floor 4+:
Implementation of ceramic walls of the central zone
Implementation of wall posts of the central zone

Floor 5+:
Implementation of wall posts of the central zone
Implementation of smoothing on the rabbets of the central zone
Implementation of defects in the facade wall

Floor 7+:
Implementation of ceramic floors of the zone Central
Execution of type, mastic and painting of the eastern zone
Execution of the substructure of the Knauf ceiling of the sterile staircase from 5+ to 7+ floors
Installation of the ceiling panel of the eastern and western zones
Execution of the elimination of defects in electrical installations
Installation and sealing of electrical panels

Floor 11+:
Execution of the ceramic body of the access corridor of the western zone
Execution of the ceramic wall of the central zone
Execution of the insulation of mechanical installations of the western zone
Installation of plenum boxes and flexi in the eastern zone
Installation of the square vent box and flexi pipe in the southern zone
Execution of the smoke control panel of the eastern zone
Execution of the substructure of the Knauf ceiling of the eastern and western zones
Execution of the fire and smoke control of the ceiling joints and electrical and mechanical elements
Execution of the elimination of defects in electrical installations
Installation of electrical panels

Floor 13+:
Execution of the ceramic wall of the wet space of the eastern zone
Execution of the Knauf wall of the gas riser
Execution of the insulation of the eastern zone bathrooms
Execution of the fire and smoke control Riser
Installation and termination of electrical panels
Perform piping and wiring in the southern zone
Performance of electrical installation defects
Installation of interior wall panels

Floor 24+:
Installation of ceiling cornice panels in the eastern zone corridor