13 May 26 Print

April 2026 News

April 2026 News

• Completion of testing of panels and bus duct lines by Lenazd Company and Tavan Tablo Mehregan Company
• Commissioning of 2 diesel generators
• Negotiation with Aryabneez Company to send cooling tower packing
• Continuation of executive operations on the hospital floors (including floors 10-11 and 13)
• Continuation of construction of project air conditioners and delivery of 51 units from Rifle Company
• Continuation of installation of project elevators and reopening of passenger elevators
• Delivery and commissioning of executive operations on the eastern side of the 17th floor + pharmacy and physiotherapy department
• Continuation of executive operations on the central zones of floors 18+ to 25+, engine room, floors 1+ to 3+, facilities of floors 16+ and the roof
• Completion of installation of all steam valves in the engine room from ARI Company
• Continuation of installation of air conditioners to the air conditioner room on floors 1+ and 1-, 3+ and 9+
• Continuation of GPON infrastructure operations on floors 11-10-7 and -1
• Continue helipad lighting operations
• Complete installation of VRFs on floors +1 and -1
• Plan for installation and commissioning of roof condensing boilers
• Continue construction of electrical panels on hospital floors
• Continue implementation of antenna reinforcement on floors of doctors' building
• Installation of diesel and diesel generator tanks on floor -2
• Complete labor camp and transfer of labor housing to floor -2
• Modify sprinklers on floor -9
• Purchase of power supply ducts to engine room panels
• Delivery process of floors 23 and 24

Floor -2:
Implementation and installation of supports and saddles
Testing of gray water tank pipes on floor +16
Implementation of diesel and diesel tank piping
Implementation of riser drain piping
Implementation of fine work, electrical and mechanical installations of workshop equipment (relocation of current workshop equipment from ground floor to 2-)

Ground floor:
Collecting pipes for labor cabin facilities (collecting workshop equipment and transferring to floor 2-)
Running earth bonding cable

Floor 7+:
Running false ceiling foundation in the eastern and western zones
Running ceiling panel installation in the western zone
Running moisture insulation in the western zone bathrooms
Running ceramic floor in the western zone wet area
Running ceramic body in the western zone access corridor
Running ceramic body in the central zone

Floor 11+:
Running cabling for sub-panels
Running electrical panels
Running ceramic body in the eastern zone access corridor
Running medical gas

Floor 13+:
Running mosaic floor in the southern and eastern zones
Running medical gas in the eastern zone
Running wiring in the southern zone
Running wall panel in the eastern zone
Running sprinkler piping

Floor 23+:
Running final ceiling paint
Running lights

Floor 24+:
Ceramic wall installation in the eastern zone wet area