• Start of testing of panels and bus duct lines by Lenazd TTM Company
• Coordination with Aryabnis Company to send cooling tower packing
• Continue execution operations on the hospital floors (including floors 10-11 and 13)
• Continue construction of project air conditioners and delivery of 51 units from Rifle Company
• Complete execution operations of the west and east sides of floor 17+ with priority for pharmacy and physiotherapy on the east side of floor 17+
• Continue execution of execution operations of the central zones of floors 18+ to 25+, engine room, floors 1+ to 3+, facilities of floors 16+ and the roof
• Delivery of all engine room steam valves from ARI Company and planning for their installation
• Continue installation of air conditioners to the air conditioner room on floor 1+ and floors -1, +3 and +9
• Continue GPON infrastructure operations on floors 11-10-7 and -1
• Continue helipad lighting operations
• Purchase of all VRFs on the floor +1 and coordination with the specialized contractor for their installation
• Installation of 2 plate converters on the 9th floor
• Continuing the service and maintenance operations of the equipment installed in the workshop with Payasazeh Company
• Continuing the construction of electrical panels on the inpatient floors
• Continuing the implementation of antenna reinforcement on the floors of the doctors' building
• Completing the dimensions of the plywood doors of the inpatient rooms of the first phase floors and coordinating with Cdoor Company to start construction
Floor -2:
Executing the central zone riser drainage piping
Installing the hardness-reducing solenoid valve
Installing the safety valve for coil sources and converters and implementing the relevant piping
Installing the solenoid valve for the concrete source and the blue-down filler
Executing the support, installing the saddle and guide
Executing the canning of the labor camp and implementing the mosaic
Executing the insulation of the sewage source and the floor of the engine room
Executing the end caps of the panels, cabling, traying and installing the support
Executing the false floor of the electrical room
Executing galvanized piping for lighting and fire alarm
Floor -1:
Executing the floor and wall ceramics
Executing Fire and smoke barriers
Condensate line installation and support and brace installation
Ceiling panel installation and wall foundation and elevator lobby ceiling foundation
Tip and mastic installation
Network cabling installation
Ground floor:
Installation of bank glass
Cementing of the east side void
Floor +7:
Sprinkler repair
Riser lock installation
Medical gas installation on the east and west sides
Ceiling foundation repair
Installation of isolated panel support
Rectification of the main cables of the panels to the central zone busduct
Network cabling installation
Floor +11:
Wall ceramic installation
Installation of electrical supports and pipes in the central zone
Floor +13:
Riser fire and smoke barriers installation
Testing and delivering galvanized lines and brace installation
Medical gas installation
Pipe insulation installation
Wall panel installation
Layer putty installation 2
Mosaic execution
Flooring execution
Installation of electrical installation supports and ceiling pipes
Floor +24:
Painting of the eastern side wall
Full mesh, wall post and falsework execution of the eastern zone
The physical progress of the entire project is 85.21%.
The implementation of the facilities has reached an overall progress of about 78%.
The implementation of mechanical and electrical installations has reached an overall progress of 80 and 75%, respectively.