• Completing internal gas piping operations and submitting documentation to the engineering system for route approval
• Continuing to install project elevators and planning to reopen passenger elevators
• Continuing to install 1 diesel generator on floor -2 and completing the relevant generator room
• Temporary handover of executive operations on the east side of floor 17+ with priority for the pharmacy and physiotherapy on the east side of floor 17+
• Continuing to construct electrical panels for the first phase of operation and delivering 150 electrical panels
• Installing all steam valves in the engine room from ARI Company
• Continuing to assemble project air conditioners in the workshop
• Planning to install and commission roof condensing boilers
• Continuing to service and maintain equipment installed in the workshop with Payasazeh Company
• Continuing to construct isolated panels by TTM Company
• Planning to purchase all project control valves
• Planning to install and operate diesel tanks on floor -2
• Planning to connect the main power supply of the project from the substation to the transformer
• Planning to Purchase of fire doors for the first phase of the project
Floor -1:
Installation of ceiling panels in the western and eastern zones
Installation of the roof substructure on the northeastern side
Installation of floor ceramics on the northeastern side
Installation of type and mastic on the southern side
Installation of wall ceramics next to the elevator on the eastern side
Installation of condensate riser lock
Installation of drain sprinkler on the northeastern side
Floor +1:
Installation of fire and smoke barriers on the elevator ceiling
Installation of cutting and installation of the eastern lorry ramp
Installation of plastering on the western side
Installation of cabling for the central and southern zone networks
Installation of support and installation of cable trays
Floor +7:
Installation of fire and smoke barriers for electrical and mechanical elements on the western side
Installation of cementing in the central zone
Installation of ceiling panels on the western side
Floor +9:
Installation of full welding of the water tank on the southern side
Installation of supports, sliders, fit-up and full welding of water supply lines on the southern, eastern and western sides
Construction of pump chassis and installation South side pump
South side collector installation
West side fan coil and air conditioner lines
Floor +10:
East zone wet area ceramic floor installation
West side ceiling panel installation
East side elevator corridor ceiling substructure installation
East side caulk and mastic installation
South side linear and square vent installation
Central zone Knauf ceiling substructure installation
Floor +17:
East side pharmacy final painting
Central zone cementing
Central zone wall ceramic tile
East side corridor ceiling substructure installation
West and central zone wiring
East side vent installation
East side exhaust fan installation
West zone cable tray installation
Floor +23:
Central zone floor ceramic tile