June 2025 News

8 August 25 Print

June 2025 News

June 2025 News

• Continue internal gas piping operations and perform pipe welding tests under the supervision of the engineering system supervisor and assign expansion loops
• Start fixing defects in the large amphitheater hall and lobby on floor +1
• Enter all remaining ducts into the workshop and prepare for installation of parts
• Planning to start the second condensing chiller on the roof
• Continue execution operations on the hospital floors (including floors 10-11 and 13)
• Continue execution operations on the west and east sides of floor 17+
• Continue execution operations on the central zones of floors 18+ to 20+
• Continue execution operations on the engine room
• Complete assembly of water tanks on floor 16+ and installation of its inlets and outlets and planning to purchase source valves
• Meeting with ARI representatives to expedite clearance of remaining steam equipment and valves from customs
• Continue execution operations on floors 1+ to 3+
• Continue installation of air conditioners in the air conditioner room on floor 1+ and floor 1-
• Continuing the assembly operations of the project's air conditioners in the workshop
• Continuing the execution operations of the helipad lighting
• Notifying the purchase contract for the roof engine room equipment from Pakman Company
• Planning to receive the cooling tower packing
• Concluding the purchase contract for two plate heat exchangers from Taha Ghaleb Toos Company
• Planning to conclude the contract on floors 8, 16 and the roof in order to complete the installation cycle
• Concluding the service and maintenance contract for the equipment installed in the workshop with Payasazeh Company

Floor 6-:
Epoxy execution

Floor 2-:
Full welding of engine room pipelines and pipe rack piping
Installation of valves, fittings, flanges, etc.
Execution of engine room pipe saddles
Execution of ironwork and installation of engine room support and tray
Execution of grease trap structure

Floor 1-:
Execution of fire and smoke barriers for the riser
Execution of walling and falsework
Execution of electrical plumbing
Execution and modification of the utility pipeline
Execution Flooring and cement work

Floor 11+:
Medical gas installation
Knauf and rock wool wall panel installation
Electrical and support plumbing installation
Floor installation

Floor 13+:
Knauf wall first face installation
Running and wall foundation installation
Sewage pipeline installation

Floor 16+:
Installation of support and cable tray

Floor 17+:
Galvanized pipe and sprinkler installation on the east side

Floor 20+:
Ceramic floor installation for the central zone service

Floor 23+:
Wall putty installation
Ceiling foundation installation
Ceiling panel installation for services
Firebox installation
Ceramic floor and body installation
Sewage pipeline installation on the east side

Floor 24+:
Southeast sewage installation
Southeast wall post and wallcrete installation
West side flooring installation
Side cementing and insulation East
Execution of body and floor ceramics
Execution of plumbing facilities on the East side

Floor 26+:
Execution of grating
Execution of roof insulation

The physical progress of the entire project is 82.99%.
The implementation of the facilities has reached an overall progress of about 74%.
The solidification and thinning operations have reached an overall progress of 81 and 63%, respectively.