  • February, March 2026 News

    4 April 26

    • Completing internal gas piping operations and submitting documentation to the engineering system for route approval• Continuing to install project elevators and planning to reopen passenger elevators• Continuing to install 1 diesel generator on floor...

  • January 2026 News

    20 February 26

    • Start of testing of panels and bus duct lines by Lenazd TTM Company• Coordination with Aryabnis Company to send cooling tower packing• Continue execution operations on the hospital floors (including floors 10-11 and 13)•...

  • December 2025 News

    2 February 26

    • Completion of internal gas piping operations and continuation of pipe welding tests under the supervision of the engineering system supervisor• Completion of installation of engine room duct parts and planning for testing of panels...

  • November 2025 News

    3 January 26

    • Complete installation of engine room pontoon components• Continue execution operations on the hospital floors (including floors 10-11 and 13)• Continue construction of the project's air conditioners and reach a progress rate of about 75%•...

  • October 2025 News

    5 December 25

    • Continuing internal gas piping operations and conducting pipe welding tests under the supervision of the engineering system supervisor and continuing the operational operationsof expansion loops• Continuing the installation of parts on the engine room...

  • September 2025 News

    7 November 25

    • Continue construction of the project's air conditioners and reach a progress rate of about 70%• Continue to fix the 22nd floor's defects• Continue to install the project's elevators• Continue to execute the 9+ floor's...