April 2023 News

10 June 23 Print

April 2023 News

April 2023 News

9th floor-:
- Implementation of joint support
- Execution of cable tray (west side)
- Implementing the sprinkler system pipe (west side)
- Implementation of water supply system piping (galvanized pipe)
- Implementation of fire system piping (firebox piping) (west side)
- Implementation of sewer pipes
- Collection of executed channels
- Implementation of the color of the wall of the eastern and western electrical room
- Execution of the floor mosaic of the eastern and western electrical room
- Installing the temporary door of the western electrical room
- Implementation of masonry wall
- Wall cementing
Grooving on the wall

2nd Floor-:
- Implementation of resin and epoxy engine room floor
- Implementation of sewer pipes
- Construction of air separator chassis
- Installing the air separator on the chassis
- Installation of cooling system flange and gasket
- Installation of cooling system valves
- Construction of cooling system collector
- Construction of expansion source chassis
- Installation of heating system flange and gasket
- Installation of heating system valves
- Making saddles for heating system piping
- Installation of saddles under the heating system piping
- Making saddles for steam system piping
- Installation of saddles for steam system piping
- Construction of steam system collector
- Implementation of steam system pipelines on supports
- Construction of electropump chassis for water supply system
- Implementation of chassis seismographs for electric water supply pumps
- Construction of electric motor chassis
- Installation of water supply system valves
- Initial installation of piping supports for the water supply system
- Construction of saddles for water supply system piping
- Installation of saddles under the water supply system piping
- Construction of water supply system collector
- Implementation of water supply system pipelines on supports
- Installing the knee of the cooling system

1st floor-:
- Installation of fresh and exhaust air channels
- Implementation of elastomeric insulation of the 5-layer pipe system
- Implementation of water supply system piping (galvanized pipe)
- Implementation of piping system of 5-layer pipes
- Constructing a positive pressure channel for the staircase
- Installing the positive pressure channel of the staircase
- Installation of return and exhaust air channels
- Implementation of the sprinkler system pipe
- Implementation of medical gas system pipe
- Implementation of fire system piping (firebox piping)
- Installation of manual dampers and fire ducts
- Implementation of pipes and cans of switches and sockets

Floor 7+:
- Implementation of pipes and cans of switches and sockets
- Implementation of wiring (lighting system)
- Implementation of cabling (network system)
- Installation of return and exhaust air channels
- Implementation of elastomeric insulation of the water supply system (galvanized pipe)
- Implementation of cabling (fire alarm system)

Floor 18+:
- Implementation of electrical tray in the corridor of the western zone
- Floor 19+:
- Implementation of electrical pipe in the wall of the dry space of offices B1 and B3
- Installation of electric pipe on the wall of the dry space of offices C1, C2, C3
- Installation of electric pipe on the dry wall of C5 and C6 offices
- Installation of electric pipe on the walls of dry spaces of A8 offices
- Implementation of electric pipe under the roof of the dry space of offices B1 to B10
- Implementation of electric pipe under the ceiling of the dry space of offices C1 to C4
- Implementation of electric pipe under the roof of the dry space of C10 and C9 offices
- Implementation of electric pipe under the roof of dry spaces of offices A1 to A6
- Implementation of electric pipe under the roof of dry spaces of A9 offices
- Implementation of electric pipe of wet space in offices B3 and B4
- Implementation of electric pipe of wet space in offices C4 and C6 to C8
- Implementation of electrical pipes in wet areas of A8 offices
- Implementation of electrical pipes in the wet areas of C1, C2, C3 offices
- Wiring and installation of switches and sockets in offices B1 and B10
- Wiring and installation of switches and sockets in offices B5 to B7
- Wiring and installation of switches and sockets in offices C1 to C10
- Wiring and brain installation of offices A1 to A10
- Fan coil piping test of western, southern and eastern zones
- Implementation of the electric pipe in the corridor of the western, southern and eastern zones
- Implementation of electrical wiring in the corridor of the western, southern and eastern zones
- Implementation of electrical pipes for corridor services in the western, southern and eastern zones
- Sewage test
- Implementation of the false ceiling panel for the dry space of the office C1 to C10
- Implementation of false ceiling panels in the dry spaces of offices A1 to A8
- Implementation of false ceiling panels in the dry spaces of C1, C2, C3 offices
- Implementation of false ceiling panels in the wet areas of offices A1 to A10
- Implementation of the ceramic body of the wet space of the office B10
- Implementation of ceramics for the body of the wet space of office B2
- Implementation of ceramics for the body of the office B4 to B9
- Implementation of ceramic floors in the dry areas of offices A1 to A9
- Implementation of ceramic floors in the wet areas of offices A1, A2, A3
- Implementation of ceramic floor of offices A4 and A7 to A9
- Implementation of the false ceiling chassis for the dry space of the office B1 to B5, B9 and B10
- Implementation of false ceiling chassis for dry spaces of C1, C2, C3 offices
- Implementation of sewage
- Implementation of the false ceiling chassis of the corridor in the southern and western zones
- Implementation of ceramics for the south zone corridor services
- Implementation of ceramics for the body of the corridor in the eastern and southern zones (on the side of the offices)
- Implementation of ceramics for the body of the corridor in the eastern and southern zones (on the side of the ducts)
- The physical progress of the whole project is 74.36%.
- The implementation of facilities related to parking lots, clinic and hospital is being implemented and the overall progress has reached about 50%.
- The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached a total progress of 55%.
- The implementation of electrical facilities related to parking lots, clinics and hospitals has reached a total progress of 46%.