July 2019 News

9 August 19 Print

July 2019 News

July 2019 News
Organize weekly engineering meetings to review project implementation issues
Conduct weekly and monthly HSE meetings and review workshop issues
Holding morning meetings in the presence of the CEO
Organize workshop meetings with project partners, employers, consultants, senior consultants and contractors
Starting and installing facade support parts
Visit Aran Saji factories to build parts of the helipad steel frame
Install friction dampers and dampers on the first to fourth floors
Preparation of the minutes of the temporary delivery of the negative floors with Behsara Company
Operation of fire protection coatings from first floor to third floor and negative floors one and two respectively by Abtik and Beta companies
Follow-up on the preparation of the floor +1 Contracts up to the 16th floor
Conducting flooring operations on the floor +1
Pre-assessment of companies for facade lighting
Follow-up of operating licenses from the municipality and related organizations