April 2021 News

7 June 21 Print

April 2021 News

April 2021 News

- Execution of wiring (lighting system), execution of floor coil +1
- Execution of elastomeric insulation of fresh air duct and +3, implementation of wiring (fire alarm system), implementation of wall cementing, implementation of wall cementing +3 floor
- Execution of support, pipes and cans of switches and sockets, implementation of wiring (fire alarm system), implementation of floor protection mortar, implementation of stone wool +4 floor
- Execution of elastomeric insulation of fresh and exhaust air ducts, installation of support and execution of return and evacuation air ducts, implementation of support and piping of water supply system (galvanized pipe), implementation of support and piping of 5-layer pipe system, implementation of elastomeric insulation of 5-pipe system Layer, implementation of pipes - medical gas system, implementation of valves, medical gas system, implementation of support, pipes and cans and sockets, - implementation of supports and cable trays, installation of support and implementation of fresh air ducts, implementation of Knauf wall substructure, Execution of perimeter knauf wall substructure, +5 floor stone wool
- Execution of pipes and cans of switches and sockets, implementation of cable trays, implementation of sewer pipes, installation of fresh air ducts, implementation of piping of water supply system (galvanized pipe), implementation of elastomeric insulation of water supply system (galvanized pipe), implementation of system piping 5-layer pipes, implementation of elastomeric insulation of 5-layer pipe system, implementation of fire system piping (firebox piping), implementation of sprinkler system pipe, implementation of medical gas system pipe +6 floor
- Execution of sewer pipes of +7 floor
- Import of 132 fan coils for floors 1 to 5 and 4 chillers and 4 boilers for the engine room
- The total progress in +1 and +2 classes is about 94%, which is about 93% in the building sector, about 86% in the electrical sector and about 99% in the mechanics sector.
- The total progress in the +3 to +5 classes is about 84%, which is about 86% in the buildings sector, about 70% in the electrical sector and about 88% in the mechanics sector.
- The facade installation operation is underway and has been completed up to the 23rd floor, and the overall progress of the project facade has reached about 80%.