July 2021 News

28 August 21 Print

July 2021 News

July 2021 News

- Floor +3:
  Execution of elastomeric insulation of water supply system (galvanized pipe), implementation of medical gas system pipe.
- Floor +4:
Execution of floor protection mortar, implementation of support, pipe and key box and socket, implementation of wiring (lighting system), implementation of wiring (electrical socket system).
- Floor +6:
Execution of pipes and boxes of switches and sockets, implementation of cable trays, implementation of piping of 5-layer pipe system, implementation of elastomeric insulation of 5-layer piping system, implementation of masonry wall, implementation of perimeter knauf wall substructure, implementation of rock wool.

- The total progress in +1 and +2 classes is about 82%, which is about 83% in the construction sector, about 68% in the electrical sector and about 89% in the mechanics sector.
- The total progress in the +3 to +5 classes is about 74%, which is about 81% in the buildings sector, about 51% in the electrical sector and about 80% in the mechanics sector.
- Hardening operations related to parking lots, clinics and hospitals are underway and the overall progress has reached about 25%.
- Joinery operations related to parking lots, clinics and hospitals are underway and the overall progress has been about 15%.