July 2022 News

1 September 22 Print

July 2022 News

July 2022 News

1st floor :
- Subframe installation
- Implementation of the infrastructure of the inner Kenaf wall
- Common support installation

Floor +1:
- Implementation of UPS system wiring

2nd floor:
- Implementation of wiring (electrical system)
- Implementation of UPS system wiring

3rd floor:
- Implementation of wiring (lighting system)
- Implementation of UPS system wiring

4th floor:
- Implementation of wiring (lighting system)
- Implementation of wiring (electrical system)
- Implementation of wiring (audio system)
- Implementation of wiring (mother clock system)

6th floor:
- Implementation of wiring (mother clock system)
- Installation of fresh and exhaust air channels

7th floor:
- Performance of stone wool
- Performing mosaics
- Carrying out cabling (summoning a nurse)

- The hardening operation related to the parking lots, clinic and hospital is being implemented and the overall progress has reached about 44%.
- Fine work operations related to parking lots, clinic and hospital are being implemented and the overall progress has reached about 28 percent.