September 2022 News

7 November 22 Print

September 2022 News

September 2022 News

Floors +3 to +7

Implementation of floor protective mortar
Implementation of waterproofing
Implementation of leaf plaster of the Kenaf wall of the second layer of the first face
Mosaic performance
Flooring of dry space
Wet space flooring
Rock wool
Implementation of leaf plaster of the first layer of the Kenaf wall MR of the wet space

Floor +18

Implementation of the false ceiling panel in the wet space of the office
Implementation of false ceiling panel in the dry spaces of the office
Painting the walls and ceilings of offices
Implementation of false ceiling panel and ceramic floor and body of corridor services in the eastern zone

Floor +9 to +16

Installation of riser air channel
Installation of riser return air channel
Fire extinguisher and sprinkler riser

17th floor to the roof

 Construction of riser air channel
Construction of riser return air channel
 Drain riser
 Galvanization riser
 Sewer riser

- The physical progress of the whole project is 70.12%.
- The hardening operation related to the parking lots, clinic and hospital is being implemented and the overall progress has reached about 48%.
- Fine work operations related to parking lots, clinics and hospitals are being implemented and have reached a total progress of about 34 percent.