October 2022 News

1 December 22 Print

October 2022 News

October 2022 News

2nd Floor-:

- Installation of cooling system flange and gasket
- Installation of cooling system valves
- Construction of expansion source chassis
- Making the chassis of the deaerator (DEAERATOR)
- Installation of saddles for steam system piping
- Implementation of steam system pipelines on supports
- Installation of soft water system piping saddles
- Construction of saddles for water supply system piping
- Installation of saddles under the water supply system piping
- Construction of water supply system collector
- Implementation of fire system pipelines on supports

1st floor-:

- Installation of fresh and exhaust air channels
- Implementation of water supply system piping (galvanized pipe)
- Implementation of piping system of 5-layer pipes
- Implementation of steel piping
- Installation of return and exhaust air channels
- Implementation of the sprinkler system pipe
- Implementation of medical gas system pipe
- Implementation of cable tray
- Implementation of pipes and cans of switches and sockets
- Implementation of the infrastructure of the inner Kenaf wall
- Implementation of leaf plaster on the wall of the first face of the inner kenaf
- Subframe installation

Floor 2+:

- Installation of support and implementation of return and evacuation air channels
- Implementation of elastometric insulation of steel pipe
- Implementation of medical gas system pipe

Floor +18 to +20:

- Implementation of the wall around the ducts of the southern zone corridor
- Implementation of ceramic flooring in the corridor of the eastern zone
- Painting the ceiling of the corridor in the eastern zone
- Implementation of the false ceiling chassis of the South Zone Corridor services
- Installing office lights
- Installation of corridor lights in the eastern zone
- Installation of Eastern Zone Firefox
- Installation of office switches and sockets
- Installation of service lights in the corridor of the western zone
- Installation of switches and sockets for the corridor services in the western zone
- Installation of corridor lights in the west zone
- Installation of western zone fireboxes
- Installation of the key, outlet in the corridor of the west zone
- Implementation of sewage piping services in the corridor of the southern zone
- Implementation of sewage piping services in the corridor of the eastern zone

- The physical progress of the whole project is 72.14%.
- The implementation of facilities related to parking lots, clinic and hospital is being implemented and the overall progress has reached about 46%.
- The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached a total progress of 51%.
- The implementation of electrical facilities related to parking lots, clinics and hospitals has reached a total progress of 42%.