November 2022 News

9 January 23 Print

November 2022 News

November 2022 News

-    1st floor-:
- Implementation of sewer pipes
- Implementation of fire system piping (firebox piping)
- Installation of manual dampers and return channel fire
- Installation of manual dampers and fire ducts
- Implementation of sewage pipes (area no. 1) floor-1

- Floor 3+ to 6+:
- Installation of support and implementation of fresh air channels
- Implementation of elastomeric insulation of fresh and outgoing air channels
- Installation of support and implementation of return and evacuation air channels

- Floor 7+:
- Implementation of medical gas system control box
- Implementation of the sprinkler system pipe
- Implementation of medical gas system valve box

- 19th floor:
- Implementation of hot and cold water piping for the wet space of the office B1 to B10
- Implementation of hot and cold water piping for the wet space of the office C10
- Implementation of hot and cold water piping for the wet area of the office C5, C6, C8, C9
- Implementation of hot and cold water piping for the wet spaces of C1, C2, C3 offices
- Execution and testing of the sewage piping in the wet area of B5 office
- Implementation of C10 office wet space sewage piping
- Implementation of sewage piping in the wet spaces of offices A1, A2, A3
- Testing the sewage piping of the wet room of the office C8 to C9
- Testing of sewage piping in the wet areas of offices A1 to A8
- Testing the sewage piping of the wet areas of offices C1 to C6
- Implementation of the piping of the fan coil in the western zone
- West zone firebox piping test
- Installation of support and implementation of sprinkler piping in the southern zone
- Testing of the sewage piping of the eastern zone corridor services
- Implementation of hot and cold water piping for eastern zone corridor services

- The physical progress of the whole project is 72.52%.
- The hardening operation related to the parking lots, clinic and hospital is being implemented and the overall progress has reached about 50%.
- Fine work operations related to parking lots, clinic and hospital are being implemented and the overall progress has reached about 39 percent.