March 2023 News

21 May 23 Print

March 2023 News

March 2023 News

9th floor:
- Implementation of EN1 and EN2 elevator wall stone wool
- Implementation of masonry wall
- Implementation of the infrastructure of the Kenaf elevator wall EN1 and EN2
- Plastering of the front wall of the EN1 and EN2 elevators
- Implementation of leaf plaster of the wall of the second face of elevator EN1 and EN2
- Wall cementing
Grooving on the wall
- Installation of plate wall post
- Wall post installation
- Implementation of elastomeric insulation of the 5-layer pipe system
- Implementation of piping system of 5-layer pipes
- Implementation of pipes and switch boxes and sockets (west side) 9th floor

Floor 1+:
- Installation of channel risers and positive pressure of the staircase

Floor 3+:
- Installation of channel risers and positive pressure of the staircase

Floor 6+:
- Implementation of floor protective mortar
- Implementation of white cement in the eastern electrical room
- Implementation of the color of the wall of the eastern electrical room
- Implementation of flooring in the eastern electrical room
- Execution of the floor mosaic of the eastern electrical room
- Implementation of white cement in the western electrical room
- Implementation of the color of the wall of the electrical room of Ghar Bay
- Implementation of flooring in the western electrical room
- Execution of the floor mosaic of the western electrical room
- Implementation of elastomeric insulation of fresh and outgoing air channels
- Construction of fresh air ducts and transportation to the installation workshop
- Installation of fresh and exhaust air channels
- Construction of return and discharge air channels and transportation to the workshop
- Construction and installation of channel risers and positive pressure of the staircase
- Implementation of cabling (fire alarm system)

Floor 17+:
- Implementation of wallcrete mesh and glue in the eastern electrical room
- Implementation of white cement in the eastern electrical room
- Implementation of flooring in the eastern electrical room
- Execution of the floor mosaic of the eastern electrical room
- Implementation of wallcrete wall of the western electrical room
- Implementation of wallcrete mesh and glue in the western electrical room
- Implementation of white cement in the western electrical room
- Implementation of flooring in the western electrical room
- Execution of the floor mosaic of the western electrical room
- Implementation of wallcrete wall of the eastern electrical room

Floor 18+:
- Mineral implementation
- Implementation of the color of the wall of the eastern electrical room
- Implementation of flooring in the eastern electrical room
- Execution of the floor mosaic of the eastern electrical room

Floor +20:
- Mineral implementation
- Implementation of wallcrete mesh and glue in the eastern electrical room
- Implementation of white cement in the eastern electrical room
- Implementation of the color of the wall of the eastern electrical room
- Implementation of flooring in the eastern electrical room
- Execution of the floor mosaic of the eastern electrical room
- Implementation of flooring in the western electrical room
- Execution of the floor mosaic of the western electrical room
- Implementation of wallcrete wall of the eastern electrical room
- Installation of channels in the western zone
- Installation of support and implementation of sprinkler piping in the western zone
- Implementation of hot and cold water piping for the corridor services in the western zone
- Cold and hot water piping test for the corridor services in the western zone
- Installation of support and implementation of sprinkler piping in the southern zone
- Piping implementation of firebox south zone
- Implementation of hot and cold water piping for the services of the South Zone Corridor
- Implementation of hot and cold water piping for the wet space of B1 office
- Implementation of hot and cold water piping for the wet space of B2 office
- Implementation of hot and cold water piping for the wet space of B3 office
- Implementation of hot and cold water piping for the wet area of office B4
- Implementation of hot and cold water piping for the wet space of B5 office
- Implementation of hot and cold water piping for the wet area of office B6
- Implementation of hot and cold water piping for the wet area of B7 office
- Implementation of hot and cold water piping for the wet space of B10 office
- Installation of support and implementation of sprinkler piping in the eastern zone

- The physical progress of the whole project is 74.14%.