March 2025 News

10 May 25 Print

March 2025 News

March 2025 News

• Execution of executive operations of the large amphitheater hall and lobby on floor +1
• Planning for the installation of low-pressure electrical panels in the engine room
• Continuing the construction of the project's air conditioners
• Temporary delivery of floor +21 and formation of the relevant commission
• Continuing the executive operations of floor -6 (parking lot)
• Continuing the lighting operations of the project's facade on the west side
• Completing the foundation of the water tanks on floor +16 and assembling them
• Continuing the construction of electrical panels on the floors of the first phase of operation
• Announcing the intended lighting plan for the helipad to RGE and obtaining its price
• Preparing the purchase contract for the remaining steam valves in the engine room
• Obtaining a proposal and price for executive operations on floors 1 to 3 from Payasazeh Company
• Transferring the air conditioner to the air conditioner room on floor +1
• Negotiating with the CEO of Rifle Company and coordinating the assembly of air conditioners
• Solving the weak current issue of the project and notifying Payasazeh Company to start and continue GPON infrastructure operations
• Setting up an escalator to access the amphitheater Theater

Floor 1+:
Decorative execution of amphitheater and lobby halls
Painting
Execution of electrical panel chassis
Execution of ceramic floor

Floor 7+:
Execution of Knauf wall
Welding

Floor 9+:
Installation of utility supports
Execution of full mesh

Floor 10+:
Execution of ceramic wall in wet area
Execution of fire and smoke barrier

Floor 11+:
Execution of duct insulation and installation of duct
Execution of wall supports and pipes
Execution of galvanized pipeline
Execution of welding

Floor 17+:
Execution of full mesh
Execution of plastering
Execution of wall cementing
Execution of deafness

Floor 22+:
Execution of window flashing
Completion of defects

Floor 25+:
Execution of central zone fan coil piping
Execution of pipes Electrical wiring and canning

The physical progress of the entire project is 82.25%.
The implementation of the facilities has reached an overall progress of about 72%.
The implementation of the mechanical and electrical facilities has reached an overall progress of 75 and 69%, respectively.