• Continue internal gas piping operations and perform pipe welding tests under the supervision of the engineering system supervisor and continue the implementation of expansion loops
• Fixing defects in the large amphitheater hall and lobby on floor +1
• Continue installing parts in the engine room ducts
• Planning for the entry of cooling tower packing
• Continue implementation operations on the hospital floors (including floors 10-11 and 13)
• Continue construction of the project's air conditioners and reaching a progress percentage of about 65%
• Continue fixing defects on floor 22
• Continue installation of project elevators
• Continue implementation operations on the west and east sides of floor 17+
• Continue implementation of implementation operations in the central zones of floors 18+ to 25+
• Continue implementation operations on the engine room
• Continue construction of electrical panels on the first phase of operation floors and delivery of 70 electrical panels
• Purchase and import of 10 steam valves related to the engine room from ARI Company
• Continue implementation operations on floors 1+ to 3+ and planning to start roof implementation Floor 1+
• Continuing the assembly operations of the project's air conditioners in the workshop
• Continuing the construction operations of the roof condensing boilers by Pakman Company
• Receiving 2 plate exchangers from Taha Ghaleb Toos Company
• Planning to conclude a contract on floors 8, 16 and the roof in order to complete the installation cycle
• Notifying the service and maintenance contract for the equipment installed in the workshop with Payasazeh Company
• Arrival of two garbage disposal devices and making preparations for installing the devices on floor 2-
• Negotiation with two automatic door supplier companies and reducing the number of doors
• Planning to purchase plywood doors for the first-phase floors' hospitalization rooms
• Opening the tender envelopes for purchasing ventilation equipment for parking lots
• Renewal of the engineering system supervisor contract
• Renewal of the fire department consultant contract

Floor 2-:
Implementation of support, saddle and guide
Implementation of condensate piping
Implementation of grease trap sewage
Implementation of cementing of the entrance to the wastewater treatment plant
Implementation of pipe rack piping

Floor 1-:
Installation of walls Knauf Services
Installation of Knauf Riser Wall Panels
Execution of Roof Substructure
Execution of Ceramic Body
Execution of Cementing

9th Floor+:
Construction of Chassis and Air Conditioner Placement
Execution of Epoxy Floor
Execution of Fit-up, Welding and Line Support

10th Floor+:
Execution of Balcony Mosaic
Execution of Ceramic Body of Wet Space
Execution of Central Zone Network Cable
Execution of False Ceiling Substructure
Execution of Ceiling Electrical Pipes

11th Floor+:
Execution of Mosaic
Execution of Knauf Wall Panel
Execution of Electrical Piping and Support
Execution of Rock Wool
Execution of Network Cabling
Execution of Medical Gas

22nd Floor+:
Execution of Final Wall Paint

23rd Floor+:
Execution of Ceiling Painting and Wall Putty
Execution of Terrace and Service Ceiling Substructure
Installation of Switches and Sockets
Execution of Ceiling Panel False
Wet space wall and floor ceramic installation
Linear light installation

Floor 24+:
Support, tray and pipe installation
Wall ceramic installation
Drain installation
Cementing installation

Floor 26+:
Grating installation
Cooling tower drain piping installation

The physical progress of the entire project is 83.71 percent.
The solidification and thinning operations have reached a total progress of 82 and 66 percent, respectively.