January 2021 News

25 February 21 Print

January 2021 News

January 2021 News

- Carrying out operations related to buildings and facilities in classes +1 to +6
- Execution of stone wool and knauf wall of floors 1+ to 5+.
- Installation of medical gas ceiling columns on the ground floor to 2+.
- Execution of wiring (lighting system and electrical outlet system) floors 1+ to 3+
- Execution of steel plumbing, support and plumbing of 5-layer systems of 4+ and 5+ floors.
- Execution of support, pipe and key box and socket and implementation of elastomeric insulation of fresh air duct of floors 3+ to +5
- Execution of 5th floor staircase and execution of 6th floor sewer pipe
- Execution of Knauf wall infrastructure, installation of subframe and installation of subframe plate of floor 6+
- Execution of stair wall cementing and execution of stair wall stone for floors 7+ to 14+
- Execution of masonry wall of 9th to 15th floors, execution of wall posts of 20+ to 24+ floors
- Execution of the stairs in the southeast of the central zone, southwest of the central zone, north of the central zone and next to the ramp.
- The total progress in the +1 and +2 classes is about 86%, which is about 83% in the building sector, about 78% in the electrical sector and about 93% in the mechanics sector.
- The total progress in the classes 3+ to +5 is about 73%, which is about 80% in the building sector, about 49% in the electrical sector and about 82% in the mechanics sector.
- The facade installation operation is underway and has been carried out up to the 21st floor.
- Operations related to firecrackers in the 1st and 2nd floors are underway and the overall progress has reached 96%.