June 2022 News

31 July 22 Print

June 2022 News

June 2022 News

5th floor- :
- Piping implementation of sprinklers

Floor 1+ to +3:
- Implementation of wiring (fan coil system)
- Implementation of wiring (mother clock system)
- Implementation of audio system wiring

4th floor:
- Implementation of support, pipe and key box and outlet
- Implementation of UPS system wiring
- Implementation of wiring (fan coil system)

5th floor:
- Implementation of support, pipe and key box and outlet
- Implementation of supports and cable tray
- Carrying out cabling (powering electrical panels from the floor)
- Implementation of wiring (lighting system)
- Implementation of wiring (electrical system)
- Implementation of UPS system wiring
- Implementation of wiring (fan coil system)
- Implementation of wiring (audio system)
- Implementation of wiring (mother clock system)

7th floor:
- Implementation of wiring (fan coil system)
- Implementation of pipes and cans of switches and sockets
- Implementation of wiring (audio system)
- Implementation of wiring (mother clock system)
- Implementation of the wall of Kenaf face 2 B, C, D
- Implementation of the wall of Kenaf face 1 C, D
- Implementation of dry space flooring
- Implementation of wiring (lighting system)
- Implementation of wiring (Prisbarg system)
- Implementation of water supply system piping (galvanized pipe)

Floor +18:
- Implementation of ceramics for the wet spaces of offices
- Installation of electrical pipes on the walls of the dry spaces of the office
- Implementation of false ceiling chassis
- Implementation of network cabling operations
- Implementation of the false ceiling chassis of the office's dry space
- Installation of support and implementation of sprinkler piping
- Implementation of body ceramics
- Implementation of dry space false ceiling chassis
- Implementation of moisture insulation in the wet space of the office
- Corridor cementing
- Implementation of C10 office wet space sewage piping
- Implementation of waterproofing services in the corridor of the eastern zone

19th floor:
- Implementation of hot and cold water piping for the wet spaces of A9 offices
- Implementation of sewage piping in the wet space of office B8

- The physical progress of the whole project is 68%.
- The implementation of facilities related to parking lots, clinics and hospitals is being implemented and the overall progress has reached about 38%.
- The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached a total progress of 43%.
- The implementation of electrical facilities related to parking lots, clinics and hospitals has reached a total progress of 34%.