• Completion of internal gas piping operations and continuation of pipe welding tests under the supervision of the engineering system supervisor
• Completion of installation of engine room duct parts and planning for testing of panels and lines of ducts
• Planning for the entry of cooling tower packing
• Delivery of the 22nd floor and operation for the presence of the owners
• Continuing the installation of project elevators and planning for the reopening of the passenger elevators
• Planning for the installation of two diesel generators on the 2nd floor and finalization of the ventilation and exhaust paths of the generators
• Continuing the construction of electrical panels for the first phase of operation floors and delivery of 140 electrical panels
• Delivery schedule for all engine room steam valves from ARI Company
• Continuing the assembly operations of the project air conditioners in the workshop
• Delivery of a condensing boiler from Pakman Company and its transfer to the roof for installation
• Commencement of construction of isolated panels by TTM Company
• Planning for the purchase of all project control valves
• Completion of the dimensions of the plywood doors of the first phase of hospital rooms
• Construction of the main workshop warehouse on the 2nd floor and planning to evacuate from the ground floor to this floor
• Holding a tender for air conditioner electrical panels and preparing a draft contract
• Delivery of all diesel tanks from Pakman Company and planning for their installation and operation
• Planning to connect the main electricity of the project from the substation to the transformer
• Planning to purchase fireproof doors for the first phase of the project
Floor 1+:
Cable laying
Ceramic installation of the central zone wall
Canning, meshing, louvers and cementing and staining the eastern ramp wall
Wall panel installation
Ceiling foundation
Medical gas installation
Floor 9+:
Fitting and full welding
Construction of water supply tank
Water supply lines
Insulation under air conditioners
Floor 10+:
Ceramic installation of the central zone wall
Ceramic installation of the elevator lobby corridor floor
Tip and mastic installation
Ceiling foundation
Installation of ceiling panels
Construction of drywall
Cable laying
Floor 16+:
Installation of hot and cold pipes
Installation of fire pipes
Installation of sewage piping
Floor 23+:
Fixing defects and supplementary operations
Floor 24+:
Installation of cement and plastering of the eastern side
Installation of falsework of the eastern side
Installation of sewage piping of the eastern side
Floor 25+:
Installation of public service doors of the central zone
The physical progress of the entire project is 84.97 percent.
The implementation of the facilities has reached an overall progress of about 77 percent.
The solidification and thinning operations have reached an overall progress of 83 and 67 percent, respectively.