November 2025 News

3 January 26 Print

November 2025 News

November 2025 News

• Complete installation of engine room pontoon components
• Continue execution operations on the hospital floors (including floors 10-11 and 13)
• Continue construction of the project's air conditioners and reach a progress rate of about 75%
• Continue fixing the defects of the 22nd floor and temporarily handing over this floor
• Continue execution operations on the 9th floor (air conditioner rooms) and continue execution of galvanized pipes to the workshop and planning to order air ducts for this floor
• Plan to install two diesel generators on the 2nd floor and meetings for ventilation and exhaust paths for generators with the supplier
• Continue execution operations on the west and east sides of the 17th floor with priority for the pharmacy and physiotherapy on the east side
• Continue execution operations on the central zones of floors 18+ to 25+
• Continue execution operations on the 6th floor (parking lot)
• Continue construction of electrical panels for the first phase of operation and delivery of 100 electrical panels
• Hold multiple meetings with the consultant BMS project regarding water vapor control valves
• Continued installation of air conditioners in the air conditioner room on floors 1+, 1-, 3+, and 9+
• Continued GPON infrastructure operations on floors 11-10-7, and -1
• Continued helipad lighting operations
• Continued construction of roof condensing boilers by Pakman Company and planning to deliver one of the boilers
• Installation of 2 plate heat exchangers on floor 9+
• Continued implementation of facilities on floors 16 and the roof
• Continued service and maintenance operations of equipment installed in the workshop with Payasazeh Company
• Installation of waste disposal devices on floor 2-
• Continued construction of the remaining 33 air conditioners and delivery of 7 devices
• Notified the contract for the project's isolated panels to TTM Company and completed shop drawings to begin construction
• Planning to purchase all project control valves
• Continued construction of electrical panels on the inpatient floors
• Continued implementation of antenna reinforcement on the floors of the doctors' building
• Arrival of all VRF equipment on floor 1-
• Beginning of dimensioning of doors Plywood for inpatient rooms on the first phase floors
• Negotiation with companies supplying fresh air equipment for parking lots to purchase equipment
• Drawing up a decorative contract for the physiotherapy units and the 17th floor pharmacy
• Meeting with Payasazeh Company regarding the relocation of the warehouse and workshop equipment from the ground floor
• Planning to notify the ground floor contract to Payasazeh Company


Floor 2-:
Executing the drainage and ventilation piping of the air conditioner and fan coil pipe
Executing the support and piping for expansion sources
Executing the busduct
Executing the galvanized piping for lighting and the tray for transformers
Executing the cementing of the incinerator room
Executing the full mesh of the incinerator room
Executing the primer and epoxy paint on the walls of the sewage tank room
Executing the sewage piping


Floor 1-:
Executing ceramic walls
Executing VRF support
Executing the plaster underlay
Executing the ceiling underlay
Executing the insulation of water supply pipes
Executing the gas Medical
Cabling, piping and wiring


Floor 7+:
Floor ceramic installation
Fireproofing and smoke protection
Panel foundation and installation
Central zone full mesh installation
Sewer piping test
Steam pipe insulation installation
Wall mastic and primer installation
Nurse call system and air conditioner thermostat installation
Network cabling installation


Floor 11+:
Wet space waterproofing
Protective mortar installation
Wall ceramic installation
2nd layer putty and ceiling foundation installation
Electrical wiring installation


Floor 13+:
Sprinkler lines, 5 layers and galvanized
Wall panel and rock wool installation
Cementing and flooring installation
Piping insulation installation
Roof support and pipes installation


Floor 17+:
Sprinkler zone installation Central
Execution of wall ceramics
Execution of plastering
Execution of cementing
Execution of wiring


Floor 23+:
Execution of plumbing and wiring
Execution of painting of vents
Execution of flooring of the central zone
Execution of floor ceramics


Floor 24+:
Execution of sealing and mastic of the central zone ceiling
Installation of linear vent of the eastern side
Execution of floor ceramics of the general service of the central zone and the corridor of the eastern zone


Floor 26+:
Execution of grating

The physical progress of the entire project is 84.56 percent.
The implementation of the facilities has reached an overall progress of about 76 percent.
The implementation of mechanical and electrical facilities has reached an overall progress of 79 and 74 percent, respectively.