June 2023 News

13 August 23 Print

June 2023 News

June 2023 News

9th floor:
- Execution of cable tray (west side)
- Implementation of elastomeric insulation of fresh and exhaust air ducts (area no. 1 and 2)
- Implementing the sprinkler system pipe (west side)
- Implementation of water supply system piping (galvanized pipe)
- Implementation of fire system piping (firebox piping) (west side)
- Implementation of steel piping
- Implementation of pipes and sockets and sockets (west side)
- Implementation of sewer pipes
- Construction of return and discharge air channels and transportation to the workshop (area no. 1 and 2)
- Construction of fresh air ducts and transportation to the installation workshop (area no. 1 and 2)
- Fan coil installation (west side)
- Installation of return and discharge air channels (area No. 1)
- Installation of fresh and exhaust air ducts (area no. 1 and 2)
- Repair and completion of galvanized pipeline
- Implementation of cement staining
- Sprinkler pipeline touch-up

8th floor:
- Implementation of the Kenaf wall around the elevator door

5th floor-:
- Installation of electrical outlets
- Filling the cracks in the parking lot floor
-    cleaning

Floor 1+:
- Implementation of rainwater pipeline
- Implementation of fire and smoke barriers
- Repairing and completing the Kenaf wall

Floor 4+:
- Construction of Omega structure in order to implement the infrastructure of the sub riser
- Runner knocking around the side riser
- Implementation of cement staining
- Modification of implemented mosaic
- Repair and completion of the medical gas pipeline
- Repairing and completing the Kenaf wall

Floor 5+:
- Implementation of wiring (lighting system)
- Implementation of wiring (electrical system)
- Implementation of the infrastructure of the modular wall of the operating room
- Implementation of the infrastructure of the modular wall of the operating room
- Implementation of operating room floor markings by the surveyor in order to implement the modular infrastructure runner
- Preparation for implementing modular wall infrastructure
- Fixing and completing the wiring
- Repair and completion of electrical pipes
- Repair and completion of cabling
- Repair and completion of electricity pipeline

Floor 6+:
- Construction of return and discharge air channels and transportation to the workshop
- Installation of return and exhaust air channels
- Installation of manual dampers and return channel fire
- Fan coil installation
- Repair and completion of the medical gas pipeline
- Implementation of fan coil support
- Runner knocking around the side riser
- Repair and completion of air ducts
- Repairing and completing the Kenaf wall
- Implementation of operating room mosaic

Floor 9+:
- Execution of the wall of the elevator hole on the 9th floor

Floor 10+:
- Implementation of tilting of the 10+ floor dock

Floor 17+:
- Plastering the walls of examination rooms in the south zone
- Implementation of ceramics for the body of the elevator wall in the south zone
- Implementation of ceramic floors in examination rooms and corridors in the south zone
- Implementation of wiring and cabling in the southern zone
- Repairing and completing the ceiling electrical piping in the south zone
- Repairing and completing sewage piping in areas that have been changed
- Repairing and completing the five-layer plumbing in the changed spaces
- Repairing and completing the sprinkler piping in the changed areas

- The physical progress of the whole project is 74.84%.
- The implementation of facilities related to parking lots, clinics and hospitals is being implemented and the overall progress has reached about 51%.
- The implementation of mechanical facilities related to parking lots, clinics and hospitals has reached a total progress of 57%.
- The implementation of electrical facilities related to parking lots, clinics and hospitals has reached a total progress of 46%.