- 95% progress in the construction of four engine room chillers by Sari Pouya Company
- Concluding a contract with Mehr Fakhr Company to supply and supply 57 elevators with the Otbis China brand.
- Preparing and arranging the contract for wall-painting operations of offices from 17th, 18th and 19th floors.
- Obtaining the approval of the perimeter of the 25th floor roof with a height of about 6 meters to cover construction facilities and equipment from Tehran Municipality.
- Selecting the project as the safe project of the city of the year and receiving a plaque of appreciation and visiting the safety committee of the engineering system of the project.
- Holding a tender for the purchase of sheets for the construction of the roof structure around the 25th floor with a tonnage of 250 tons and notifying the execution agenda for construction to Aran Sage Company within a period of 60 days.
- Concluding a contract for resources, tanks and engine room directors with Pak Man Company.
- Preparation of a draft contract for the implementation of the hospital's high voltage electricity network with a bus duct mechanism with Lenizd company from the 2nd to the 25th floor.
- The skeleton of +26 floor is being executed and installed.
- Operations related to buildings and facilities in the +1 to +2 floors are underway and the overall progress has reached 77%.
- Operations related to buildings and facilities in the +3 to +5 floors are underway and the overall progress has reached 50%.
- Notification of the contract related to the construction of buildings and facilities of the sixth floors.
- Operations related to the buildings of the central zone from +7 to +16 floors are underway.
- The installation of the ground floor facade project has been carried out up to the 26th floor and up to the 15th floor, and the overall progress has reached 54%.
- Fire-related operations on the ground floor to +26 have been carried out and completed.
- Fire-related operations are being carried out on the 1st and 2nd floors, and the overall progress has reached 86%.