News

  • June 2026 News

    12 July 26

    • Installation and placement of roof engine room equipment• Continuation of executive operations on the hospital floors (including floors 10-11 and 13)• Continuation of executive operations on the central zones of the floors, engine room,...

  • May 2026 News

    11 June 26

    • Completing the internal gas piping operations and submitting the documentation to the engineering system for route approval• Continuing the construction of electrical panels for the first phase of operation and delivery of all electrical...

  • April 2026 News

    13 May 26

    • Completion of testing of panels and bus duct lines by Lenazd Company and Tavan Tablo Mehregan Company• Commissioning of 2 diesel generators• Negotiation with Aryabneez Company to send cooling tower packing• Continuation of executive...

  • February, March 2026 News

    4 April 26

    • Completing internal gas piping operations and submitting documentation to the engineering system for route approval• Continuing to install project elevators and planning to reopen passenger elevators• Continuing to install 1 diesel generator on floor...

  • January 2026 News

    20 February 26

    • Start of testing of panels and bus duct lines by Lenazd TTM Company• Coordination with Aryabnis Company to send cooling tower packing• Continue execution operations on the hospital floors (including floors 10-11 and 13)•...

  • December 2025 News

    2 February 26

    • Completion of internal gas piping operations and continuation of pipe welding tests under the supervision of the engineering system supervisor• Completion of installation of engine room duct parts and planning for testing of panels...