News

  • January 2021 News

    25 February 21

    - Carrying out operations related to buildings and facilities in classes +1 to +6- Execution of stone wool and knauf wall of floors 1+ to 5+.- Installation of medical gas ceiling columns on the ground...

  • December 2020 News

    25 January 21

    - Carrying out operations related to buildings and facilities in +1 to +6 floors- Execution of waterproofing of floors 1+ to 3+ and execution of stone floor of floors +1 to +4- Execution of cementing...

  • November 2020 News

    27 December 20

    - Operations related to buildings and facilities in the +1 to +6 floors are underway.- The total progress in the +1 and +2 classes is about 90%, which is about 91% in the buildings sector,...

  • October 2020 News

    2 December 20

    - Operations related to buildings and facilities in the +1 to +5 floors are underway.- The total progress in the +1 and +2 classes is about 77%.- The total progress in the +3 to +5...

  • September 2020 News

    10 November 20

    - 95% progress in the construction of four engine room chillers by Sari Pouya Company- Concluding a contract with Mehr Fakhr Company to supply and supply 57 elevators with the Otbis China brand.- Preparing and...

  • August 2020 News

    10 November 20

    - Execution of 400 units in the facade equivalent to 2000 square meters- Execution of operations of buildings and facilities in floors +1 to +5- Holding HSE meetings- Holding weekly and continuous meetings with contractors-...