News

  • April 2023 News

    10 June 23

    9th floor-:- Implementation of joint support- Execution of cable tray (west side)- Implementing the sprinkler system pipe (west side)- Implementation of water supply system piping (galvanized pipe)- Implementation of fire system piping (firebox piping) (west...

  • March 2023 News

    21 May 23

    9th floor:- Implementation of EN1 and EN2 elevator wall stone wool- Implementation of masonry wall- Implementation of the infrastructure of the Kenaf elevator wall EN1 and EN2- Plastering of the front wall of the EN1...

  • February 2023 News

    1 May 23

    1st floor-   :- Implementation of elastomeric insulation of fresh and outgoing air channels- Installation of fresh and exhaust air channels- Implementation of elastomeric insulation of the 5-layer pipe system- Implementation of water supply system piping...

  • January 2023 News

    8 March 23

    2nd Floor- :- Implementation of sewer pipes- Installation of cooling system valves- Construction of electric motor chassis- Construction of the knee of the steam systemFloor 3+:- Implementation of elastomeric insulation of the water supply system...

  • December 2022 News

    29 January 23

    2nd Floor-  :- Installing the flange and gasket of the cooling and heating system- Implementation of cooling system pipelines on supports- Construction and installation of heating system piping saddles- Installation of steam system flange and...

  • November 2022 News

    9 January 23

    -    1st floor-:- Implementation of sewer pipes- Implementation of fire system piping (firebox piping)- Installation of manual dampers and return channel fire- Installation of manual dampers and fire ducts- Implementation of sewage pipes (area no....