News

  • July 2021 News

    28 August 21

    - Floor +3:  Execution of elastomeric insulation of water supply system (galvanized pipe), implementation of medical gas system pipe.- Floor +4:Execution of floor protection mortar, implementation of support, pipe and key box and socket, implementation...

  • June 2021 News

    21 July 21

    - Floor +2Installation of support and implementation of fresh air ducts, elastomeric insulation of fresh air ducts, implementation of support and plumbing of 5-layer pipe system, implementation of elastomeric insulation of 5-layer pipe system, implementation...

  • May 2021 News

    2 July 21

    - Floors +1 to +4Execution of valve of medical gas system, cement facade of +1 floorExecution of fan coil, installation of support and execution of fresh and departure air ducts, construction of return air ducts...

  • April 2021 News

    7 June 21

    - Execution of wiring (lighting system), execution of floor coil +1- Execution of elastomeric insulation of fresh air duct and +3, implementation of wiring (fire alarm system), implementation of wall cementing, implementation of wall cementing...

  • March 2021 News

    6 May 21

    - Execution of elastomeric insulation of water supply system of +4 floor and execution of fan coil of +3 and +4 floors.-Support bricks, pipes and key boxes of +4 and +5 floors and execution of...

  • February 2021 News

    23 April 21

    - Carrying out operations related to buildings and facilities in +1 to +6 floors- Execution of masonry wall of floors +3 to +6 and floors +17 to 23.- Execution of Knauf wall leaf plaster of...