News

  • October 2022 News

    1 December 22

    2nd Floor-:- Installation of cooling system flange and gasket- Installation of cooling system valves- Construction of expansion source chassis- Making the chassis of the deaerator (DEAERATOR)- Installation of saddles for steam system piping- Implementation of...

  • September 2022 News

    7 November 22

    Floors +3 to +7Implementation of floor protective mortarImplementation of waterproofingImplementation of leaf plaster of the Kenaf wall of the second layer of the first faceMosaic performanceFlooring of dry spaceWet space flooringRock woolImplementation of leaf plaster...

  • August 2022 News

    9 October 22

    2nd Floor :- Implementation of the motor house loop structure- Construction of condensate source water supply collector- Construction of air separator chassis (AIR SEPARATOR)- Installation of cooling system flange and gasket- Installation of strainer and...

  • July 2022 News

    1 September 22

    1st floor :- Subframe installation- Implementation of the infrastructure of the inner Kenaf wall- Common support installationFloor +1:- Implementation of UPS system wiring2nd floor:- Implementation of wiring (electrical system)- Implementation of UPS system wiring3rd floor:-...

  • June 2022 News

    31 July 22

    5th floor- :- Piping implementation of sprinklersFloor 1+ to +3:- Implementation of wiring (fan coil system)- Implementation of wiring (mother clock system)- Implementation of audio system wiring4th floor:- Implementation of support, pipe and key box...

  • May 2022 News

    5 July 22

    Negative floors and ground floor:- Implementation of the masonry wall of the 4th floor-- Implementation of EN7 and EN13 elevator wall paint on the ground floor- Implementation of Kenaf EN7 wall color on the ground...